File #: REP 15-364    Version: 1 Name: Change Order 1 for WS-756
Type: Informational Report Status: Meeting Item
File created: 7/14/2015 In control: CITY COUNCIL WORKSHOP
On agenda: 7/20/2015 Final action:
Title: NW 6th Avenue Water and Storm Sewer Improvements Change Order Details: Change Order No. 1 is for the removal of an unidentified pipe and associated standby time and for unanticipated required excavation and haul of unsuitable material and additional imported material. The cost for this additional work is $8,893.60 and is funded by the General Obligation Bond. Presenter: James Carothers, Engineering Manager
Attachments: 1. NW 6th Water & Storm Change Order 1
Related files: AI 15-286, AI 15-209, AI 15-352, AI 15-311, AI 15-312, REP 15-426, AI 16-116, AI 15-346
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

NW 6th Avenue Water and Storm Sewer Improvements Change Order

Details: Change Order No. 1 is for the removal of an unidentified pipe and associated standby time and for unanticipated required excavation and haul of unsuitable material and additional imported material. The cost for this additional work is $8,893.60 and is funded by the General Obligation Bond.

Presenter: James Carothers, Engineering Manager

Recommended Action

Recommended Action: Staff recommends this item be placed on the August 3, 2015 Consent Agenda for Council's consideration.