File #: REP 15-426    Version: 1 Name: WS-756 Change Order 2
Type: Informational Report Status: Meeting Item
File created: 9/1/2015 In control: CITY COUNCIL WORKSHOP
On agenda: 9/8/2015 Final action:
Title: NW 6th Avenue Water and Storm Sewer Improvements Change Order No. 2 for WS-756 Details: This second project change order is for the repair of two undocumented pipes, the required modification of a newly installed catch basin, and materials and standby time associated with the discovery of a differing valve connection. This change order removes a number of unused items from the project resulting in a net credit for this change order. The cost for this additional work is ($9,552.76) and is funded by the General Obligation Bond. Presenter: James Carothers, Engineering Manager
Attachments: 1. NW 6th Utilities Change Order 2
Related files: AI 15-312, REP 15-364, AI 15-209, AI 15-286, AI 15-311, AI 16-116, AI 15-352, AI 15-346
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

NW 6th Avenue Water and Storm Sewer Improvements Change Order No. 2 for WS-756

Details: This second project change order is for the repair of two undocumented pipes, the required modification of a newly installed catch basin, and materials and standby time associated with the discovery of a differing valve connection. This change order removes a number of unused items from the project resulting in a net credit for this change order. The cost for this additional work is ($9,552.76) and is funded by the General Obligation Bond.

Presenter: James Carothers, Engineering Manager

Recommended Action

Recommended Action: Staff recommends this item be placed on the September 21, 2015 Consent Agenda for Council's consideration.