Consultant Services for North Urban Growth Area (NUGA) Sewer Transmission System Design
Details: OTAK Inc. was selected through a Request for Proposal process to provide civil engineering design services for the NUGA Sewer Transmission System. Staff has elected to have the consultant complete the project in two phases; the first being completion of a 30% design effort prior to moving forward with final engineering plans, specifications and estimates. This approach is due to the complexity of the project and key elements of the project that need to be addressed before moving forward on final design. OTAK, Inc. has submitted a scope of services and fee for the 30% project design in the amount of $1,089,773. The schedule for 30% design includes completion by March of 2016 with an anticipated final design being completed by February of 2017. The project will be funded with the 2015 Water/Sewer Revenue Bonds, which are supported by the City's current rate structure.