NW 6th Avenue Water and Storm Sewer Improvements Change Order
Details: Change Order No. 1 is for the removal of an unidentified pipe and associated standby time and for unanticipated required excavation and haul of unsuitable material and additional imported material. The cost for this additional work is $8,893.60 and is funded by the General Obligation Bond.