North Shore Sewer Transmission System Construction Contract
Details: On March 23, 2017, the City received four bids for the North Shore Sewer Transmission System construction project. Contractors who submitted bids were Tapani Inc., Nutter Corporation, Rotschy Inc. and Wildish Standard Paving Company. The bid proposal was divided into two separate schedules, one being the Basis of Award for the overall project and the second being Additive A for the 43rd Avenue Storm Pipe and Ditch Fill. The engineers estimate for each was $12,644,120.51 and $91,099.36; respectively. A low bid was submitted by Rotschy Inc. in the amount of $10,420,385.33 for Basis of Award and $56,509.46 for Additive A. Staff recommended that Rotschy Inc. be awarded the construction contract for the North Shore Sewer Transmission System for both the Basis of Award and Additive A in the amount of $10,420,385.33 and $56,509.46. This project is funded through previously approved bond proceeds. The Camas School District w...
|