File #: REP 16-122    Version: 1 Name: Water - Steigerwald Wellfield
Type: Informational Report Status: Meeting Item
File created: 3/16/2016 In control: CITY COUNCIL WORKSHOP
On agenda: 3/21/2016 Final action:
Title: Steigerwald Lake Restoration Project and Steigerwald Wellfield Development Update Details: Staff provided an update to the City Council regarding the Steigerwald Lake Floodplain Restoration Project being sponsored by the Bonneville Power Administration (BPA) and led by the Lower Columbia Estuary Partnership and the Port of Camas-Washougal. The presentation also included information regarding concerns that have been raised by Washougal and Camas staff associated with the siting of the proposed future wellfield site in relation to the restoration project and ongoing coordination efforts with the Restoration Project Team. Presenter: Sam Adams, Utilities Manager and Steve Wall, Public Works Director
Attachments: 1. Steigerwald Lake Restoration Project Presentation
Related files: REP 15-401, REP 15-335, AI 15-328
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Steigerwald Lake Restoration Project and Steigerwald Wellfield Development Update

Details: Staff provided an update to the City Council regarding the Steigerwald Lake Floodplain Restoration Project being sponsored by the Bonneville Power Administration (BPA) and led by the Lower Columbia Estuary Partnership and the Port of Camas-Washougal. The presentation also included information regarding concerns that have been raised by Washougal and Camas staff associated with the siting of the proposed future wellfield site in relation to the restoration project and ongoing coordination efforts with the Restoration Project Team.

Presenter: Sam Adams, Utilities Manager and Steve Wall, Public Works Director

Recommended Action

Recommended Action: This item is for Council's information only.