Title:
|
Accepted the Mill Ditch Sewer Main Replacement Project as complete. The total construction contract amount paid was $417,105.25. The final pay estimate was paid on April 2, 2018. This project is funded by the Sewer Utility Fund. The 2018 budget allocation for this project will be covered in the Spring Omnibus. (Submitted by James Carothers)
|