File #: REP 16-083    Version: 1 Name: Water Treatment Plant Construction
Type: Informational Report Status: Meeting Item
File created: 3/1/2016 In control: CITY COUNCIL WORKSHOP
On agenda: 3/7/2016 Final action:
Title: Slow Sand Water Treatment Plant Change Order Details: Change Order No. 2 for the water treatment plant project is for several miscellaneous items including a septic tank design and installation of additional parking lot drainage. The cost of this change order is $66,660.07 and is funded by a Washington State Department of Health (WSDOH) Drinking Water State Revolving Fund (SRF) loan and is included in the 2016 Budget. This change order increases the project cost by 1.13%. The total of all change orders to date is 1.83% of the original contract bid. Presenter: James Carothers, Engineering Manager
Attachments: 1. Slow Sand Water Treatment Plant Change Order No. 2
Related files: REP 15-428, AI 16-043, AI 15-348, AI 16-261
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Slow Sand Water Treatment Plant Change Order

Details:  Change Order No. 2 for the water treatment plant project is for several miscellaneous items including a septic tank design and installation of additional parking lot drainage. The cost of this change order is $66,660.07 and is funded by a Washington State Department of Health (WSDOH) Drinking Water State Revolving Fund (SRF) loan and is included in the 2016 Budget. This change order increases the project cost by 1.13%. The total of all change orders to date is 1.83% of the original contract bid.

Presenter: James Carothers, Engineering Manager

Recommended Action

Recommended Action:  Staff recommends this item be placed on the March 21, 2016 Consent Agenda for Council's consideration.