Title:
|
North Hills Subdivision Improvements and Impact Fee Credits Approval
Details: A developer is entitled to credit against the applicable impact fee for dedication of land, engineering or construction of impact fee eligible improvements as determined in the Camas Capital Facilities Plan. Camas Municipal Code (CMC) 3.88.140A(5)(A) states that impact fee creditable work is to be accepted by the City Council prior to credits being granted. The developer of the North Hills Subdivision was required to construct a regional trail that was identified as a Park Impact Fee creditable improvement. In this circumstance, the creditable improvements include the cost for constructing a sidewalk that is 4 feet wider than required; the overall widened sidewalk will serve as part of the regional trail network. The available Park Impact Fee credits are only for the cost of the additional 4 feet in width. The Transportation Impact Fee creditable improvements for this development include the construction of a...
|