Project S-565 NW 38th Avenue Phase 2 Roadway Improvements, Change Order No. 5
Details: Pavement striping removal was performed by the contractor in June 2015. This removal was required in order to properly match striping between phases 1 and 2. It was recently brought to staff's attention that the original contract approved by Council did not include a "Removing Paint Line" bid item. This change order reimburses the contractor, Nutter Corp., $939.62 for this work. This cost is being funded by the general obligation bond.
Presenter: James Carothers, Engineering Manager
|