Sewer Transmission Main Consultant Contract Supplement
Details: The STEP sewer transmission main route bisects areas of archaeological significance. Efforts were made during project design to keep these areas of potential archaeological finds to a minimum. There are two areas that require additional archaeological investigation and artifact curation. The cost of this additional consultant work is $175,646. This additional cost is covered by the Public Works Trust Fund loan for this project.
Presenter: James Carothers, Engineering Manager
|