BergerABAM Preliminary Engineering North Urban Growth Area (NUGA) Sewer Service Alternative Analysis Consultant Services Supplemental Budget
Details: BergerABAM has been under contract since September 2014, to support the City of Camas efforts for the North Urban Growth Boundary Sewer Alternatives Analysis. Their existing Scope of Services No. 2 approved on October 20, 2014, in the amount of $77,475.00, has been spent. Several months ago, staff asked BergerABAM to edit report figures and update graphics in support of the project. This additional work was conducted outside of BergerABAM's original scope of services. BergerABAM requested approval of a supplemental budget in the amount of $1,225.00. There is sufficient budget in the Water/Sewer Fund to cover these additional expenses.