File #: REP 15-427    Version: 1 Name: WS-714 Change Order 1
Type: Informational Report Status: Meeting Item
File created: 9/1/2015 In control: CITY COUNCIL WORKSHOP
On agenda: 9/8/2015 Final action:
Title: STEP Sewer Transmission Main Project Change Order No. 1 for WS-714 Details: This change order is for the addition of two sanitary sewer services at the control building for wells 10, 11 and 12, for Concrete Products, additional brush clearing not called out in the plans, and excavation for additional required archaeological investigation. The cost for this additional work is $13,354.68 and is funded by a Public Works Trust Fund loan. Presenter: James Carothers, Engineering Manager
Attachments: 1. Sewer Transmission Main Change Order 1
Related files: AI 15-248, AI 15-315, AI 15-173, AI 15-183, AI 15-208, AI 15-409, AI 15-372, AI 15-347, AI 15-353, REP 16-085
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

STEP Sewer Transmission Main Project Change Order No. 1 for WS-714

Details: This change order is for the addition of two sanitary sewer services at the control building for wells 10, 11 and 12, for Concrete Products, additional brush clearing not called out in the plans, and excavation for additional required archaeological investigation. The cost for this additional work is $13,354.68 and is funded by a Public Works Trust Fund loan.

Presenter: James Carothers, Engineering Manager

Recommended Action

Recommended Action: Staff recommends this item be placed on the September 21, 2015 Consent Agenda for Council's consideration.